Create a bill of materials in MRPeasy

Define the components and quantities needed to make one unit, then check a manufacturing order against the bill of materials.

Updated 7.32 min

Steps

  1. In Stock, create the finished product and the component items you want to consume. Check each unit of measure.
  2. Open the manufactured item and create a bill of materials. Add each component and the quantity required for one finished unit.
  3. For a subassembly, define its own manufactured item and bill of materials, then add it as a component of the parent product.
  4. Create a test manufacturing order for a few units and check the required component quantities before confirming production.

What to check

A bill of materials defines what gets consumed. Use routing to specify the workstations and operations needed to manufacture it.

See the MRPeasy profile on QAILT.